Springdale Data Center County Review Flags Generators and Cleanup

The Springdale data center is now in Allegheny County’s hands, and the county’s first review found a long list of problems. Allegheny DC Propco LLC wants to build a data center campus on 47.53 acres of the old Cheswick power plant site at 151 Porter Street. The plan also calls for about 200 permanent jobs and diesel generators along a street lined with houses. Residents have until Monday, November 30, 2026, to send the county written comments.

Last December, we covered the borough side of this fight in Springdale Council Votes on Springdale Data Center. Since then, the borough has granted the project a conditional use approval, and the developer has filed its site plan with the county. This update covers where that review stands.

Why the County Is Reviewing the Springdale Data Center

Springdale has no subdivision and land development ordinance of its own. Because of that, the county’s 2012 ordinance applies, and the Planning Division of Allegheny County Economic Development runs the review. Allegheny DC Propco then filed its preliminary land development plan with the county on June 22, 2026.

The county’s Springdale Data Center project page posts the whole file. That includes the plan set, the application packet, a stormwater narrative, a geotechnical report and three review letters: one from the county, one from consultant Mackin and one from the borough.

Even so, the developer has not said how much power the campus would use or what it would cost.

What the County Review Letter Found

On September 16, 2026, the county sent the developer’s engineers a detailed review letter. It lists what is missing or has to change before the plan can move forward. In particular, several items stand out for neighbors.

Generators Across From Homes

The site plan puts diesel generators at ground level on concrete pads along Porter Street, across from houses. That is a change from the conditional use application, which instead showed them on the roof and covered. The county also noted that no noise modeling and no generator testing schedule were submitted.

The borough’s conditional use approval caps everyday noise at 85 decibels at the property line. Emergency generators, though, are allowed to run between 85 and 115 decibels.

Smokestacks in Springdale, Pennsylvania, in June 2023, site of Springdale data center

Contamination and Health Department Sign-Off

The plans show arsenic and methylnaphthalene contamination in areas the project would disturb. However, no cleanup plan approved by the state Department of Environmental Protection was submitted. The county also found no written certification from the Allegheny County Health Department, and the letter says the applicant had not contacted the department yet.

A Cemetery Inside the Site

The St. Mark’s Lutheran Church cemetery sits in the middle of the property. Today, people reach it by a 16-foot easement from Pittsburgh Street. The plan would close that route and bring access in from Duquesne Avenue instead, across a bridge over Tawney Run that does not appear on the plans. In addition, no consent from the church was provided, and the cemetery’s boundary is disputed. The new cemetery lot would have four parking spaces.

Ownership, Parking and the Trail

The county found other gaps too. For example, one parcel inside the plan belongs to Duquesne Light and holds a substation, and the owner listed on the cover sheet does not match the parcel records.

The plan narrative lists about 200 permanent employees and 200 parking spaces. But only 140 of those spaces sit inside the data center fence, and the county says only those can count toward employee parking. The other 60 are in a lot for the trail.

That trail is the Three Rivers Heritage Trail, which runs along the site. The developer asked to narrow its easement from 10 feet to 8, but the county says a multipurpose trail needs 20. The county also wants a crosswalk on Duquesne Avenue leading to Rachel Carson Park.

Springdale Data Center Timeline

Date Step
December 2025 Springdale Borough Council takes up the project
June 22, 2026 Developer files its preliminary land development plan with the county
September 16, 2026 County sends its review letter
October 14, 2026 Virtual public meeting
October 28, 2026 In-person public meeting at the Springdale Borough Municipal Building
November 30, 2026 Last day for written public comments

How to Send the County a Comment

Written comments go through the registration form on the county’s project page. Comments that arrive after November 30, 2026 may not make it into the meeting record, so send yours early. The county also says it will announce more chances to comment as the review goes on, and its Planning Division takes questions by email.

What It Means for Allegheny Valley Homeowners

Data centers are being planned across Western Pennsylvania, and our Pittsburgh data center map shows how many. In Springdale, the houses on and near Porter Street sit closest to the generator pads, so they would feel the effects first. As a result, buyers looking at homes there are likely to ask about noise, construction traffic and the cleanup.

At the same time, 200 permanent jobs would be a big employer for a small borough. Still, for now the county’s letter describes a plan with a lot left to fix. So if you live nearby, the November 30 deadline is your next chance to get your questions on the record.

FAQs

Where is the Springdale data center planned?

At 151 Porter Street in Springdale Borough, on 47.53 acres of the former Cheswick power plant site along the Allegheny River.

Who wants to build the Springdale data center?

Allegheny DC Propco LLC. It filed a preliminary land development plan with Allegheny County on June 22, 2026.

Why is Allegheny County reviewing it instead of Springdale?

Springdale has no subdivision and land development ordinance, so the county’s ordinance applies. Before the county review, the borough granted a conditional use approval with conditions such as noise limits.

How loud can the Springdale data center be?

The borough’s conditional use approval limits everyday operation to 85 decibels at the property line. However, emergency generators may run at 85 to 115 decibels.

How can I comment on the Springdale data center?

Send written comments through the registration form on Allegheny County’s Springdale Data Center project page by Monday, November 30, 2026.

Selling a House Near Porter Street?

Reviews like this can drag on for months, and nobody can say yet what the finished project will look and sound like. If you would rather sell your house without the hassle of waiting it out, Buys Houses buys houses as-is in Springdale, Cheswick and across the Allegheny Valley.

You won’t need to fix anything or clear the place out, and we cover the closing costs. Get a cash offer today, or call or text 412-561-9833 to talk it through with our team.